Conservation of turboset by warmed air.

Turbine equipment, paused for longer than seven days, should be subject to mandatory conservation.
  Conservation turboset by warmed air is carried out in order to protect the metal sites turbine stop and control valves, condensers and pipelines from corrosion parking. The protection is done by reducing the humidity, which is in the cavities of consecrating equipment. To this end, the first selection of high-pressure cylinder on air with a blower forcibly fed air to the radiator heated to a temperature necessary to ensure the moisture content no higher than 40%. Regulators and shut-off valves, high and medium pressure open. Release air from the cavities turboset is made through compression cylinder turbines, through an open gate breakdown in the vacuum condenser, through additional pipes for air.
  Application of conservation turboset warmed the air to ensure reliable protection of equipment stopped from parking corrosion during the period of conservation.
  Compared with the equipment, which does not apply conservation:
- Significantly reduced the likelihood of cracking of metal under stress;
- To prevent erosion-corrosion processes;
- Increases reliability, increases lifespan and overhaul life between all equipment power unit;
- Increasing the efficiency of the condenser;
- Increases efficiency of equipment.
In includes heater and fan.
The program of work includes:
• Development of technical documentation on changes and additions to the thermal pattern.
• Development of technical documentation on changes and additions in the scheme of control and management.
• Develop guidelines for conservation turboset by warmed air.
• Technical management implementation projects.
• Technical guidance on the conservation of the turbine
A detailed techno-commercial offer, you can receive, send an e-mail mail@lenturbo.ru or fax (812) 531-20-20 


17.04.2009

The company has obtained the Certificate of compliance of System of a quality management (ISO 9001:2000)

15.01.2009
Lenturboremont” ltd secured the status of Technical agent of “Jakutskenergo”Corp
30.12.2008

“Lenturboremont” ltd. fulfilled preliminary specifications for works such as:
Change of К-200-130 turbounit parts and junctions, station №11 Verkhne-Tagilskaya ГРЭС

10.10.2008

The works have finished on the ПС 330 кВ КМСК

Ltd. “ETF"LENTURBOREMONT" is not responsible for the unauthorized use of any information contained in this site