New technology of start-up of the turbine from a cold condition pre-push warming up and check of vacuum density turbounit superfluous pressure of steam without filling of steam space of the condenser with water

Pre-push running up to a temperature of 110-120C ˚ prevents the cold brittleness of rotors, reducing to a minimum shutter speed at the intermediate frequency of rotation, for an up, which reduces the start time of 50 or more minutes for the various types of turbines, and reduces the loss of fuel launchers. 
The proposed package of works includes: 
- Development of technical documentation for changes and additions the thermal circuit of turboset. 
- Development of guidelines for new technology of start-up and verification of turbine vacuum density. 
- Technical guidance on changes in the thermal circuit. 
- Management of starting the turbine from a cold state of the new technology and participate in the test vacuum system. 
A detailed techno-commercial offer, you can receive, by sending an e-mail mail@lenturbo.ru or fax (812) 531-20-20
 


17.04.2009

The company has obtained the Certificate of compliance of System of a quality management (ISO 9001:2000)

15.01.2009
Lenturboremont” ltd secured the status of Technical agent of “Jakutskenergo”Corp
30.12.2008

“Lenturboremont” ltd. fulfilled preliminary specifications for works such as:
Change of К-200-130 turbounit parts and junctions, station №11 Verkhne-Tagilskaya ГРЭС

10.10.2008

The works have finished on the ПС 330 кВ КМСК